Advertisement

Talanta Stadium: Government Provides Update Amid Missed Completion Deadline

Defence CS Soipan Tuya during an inspection tour of Talanta Stadium. Photo: Soipan Tuya/X
The state has issued the latest on the progress of construction work on Talanta Stadium which is 88 per cent complete as Kenya prepares for the 2027 Africa Cup of Nations.
Advertisement

The government has provided a progress report on the construction of the Talanta Stadium after the project missed its initial March completion target.

Advertisement

The state-of-the-art facility is a key government initiative aimed at elevating Kenya's sporting infrastructure. President William Ruto presided over the ground-breaking ceremony in March 2024, with the project initially overseen by then-Sports Cabinet Secretary Ababu Namwamba.

Construction of the stadium is a critical component of Kenya's preparations to co-host the 2027 Africa Cup of Nations (AFCON) alongside Uganda and Tanzania.

Advertisement

With the project running behind schedule, Cabinet Secretary for Defence Soipan Tuya visited the site to assess the progress on Thursday.

Defence CS Shares Construction Progress

“The Stadium is at 88 percent complete with the main structural works completed and current efforts are focused on final works to make the stadium fully operational and compliant with international standards and in readiness for AFCON 2027,” Tuya updated via a social media post.

“While the Kenya Defence Forces are overseeing construction of the stadium, complementary infrastructure in transport, energy, ICT, and water is progressing through a coordinated, whole-of-government approach.”

Advertisement

Originally scheduled for completion by December 31, 2025, the deadline was pushed to March 31, 2026, due to unforeseen delays. With 12% of the work still remaining, a new official completion date has not yet been announced.

The main contractor, China Road and Bridge Corporation (CRBC), is reportedly working around the clock to finish the project.

Photos shared by Tuya show that the stadium's facade and roofing are complete, featuring distinctive Kenyan shield designs that add a cultural touch to the modern structure. The installation of seating is also well underway, beginning with the VIP sections.

Advertisement

Key Installations Made So Far

The choice of seats has been the subject of public criticism, particularly concerning the high cost of the stadium. The general seating areas will feature seats with backrests but will not be foldable. In contrast, the VIP sections are being fitted with foldable seats, similar to the arrangement at Kasarani Stadium.

Images indicate that seating in the lower tier is largely finished, with significant progress made on the upper tier as well. The middle tier, which will house the VVIP section and presidential suite, will be fitted last. This area will feature premium, cushioned conference-style seats with cup holders and more legroom, reserved for the President and top Confederation of African Football (CAF) officials.

Advertisement

The photos also reveal the installation of large LED screens behind the goal areas, a CAF requirement for stadium announcements, replays, and potential Video Assistant Referee (VAR) displays. Work on the playing surface is ongoing, though the final layer of soil for grass planting has not yet been laid.

Outside the main structure, landscaping is at an advanced stage, with paving stones installed on major pathways and grass planted to enhance the facility's aesthetic.

Advertisement